The 2.8 km long road will connect Valeriy Lobanovsky Avenue with the airport in Solomyansky district.
The project involves the construction of a two-lane road, a bicycle lane, sidewalks, safety lanes, an overhead pedestrian crossing, as well as the installation of traffic lights, sewage treatment plants, and retaining walls.
Construction is scheduled to be completed by July 2026. Funding will be limited in 2024, UAH 1.16 billion is planned for 2025, and the rest in 2026.
Four companies took part in the tender, including Ukratomenergobud, whose cheapest offer (1.36 billion UAH) was rejected due to documentation problems. As a result, the winner was the Mostador Group consortium with an offer of UAH 1.47 billion.
The consortium includes six companies, including Bridge Construction Unit No. 112 and KP Shlyakhbud Invest, which will provide the main resources for construction. The total income of the consortium members in 2023 amounted to UAH 2.09 billion.
Asphalt concrete will be supplied by BK Zorya LLC, and the main works will be performed by Shlyakhbud Invest and Bridge Construction Unit No. 112.
As Our Money found out, in the information of resources, the largest amount – UAH 92.26 million – is provided for fine-grained asphalt concrete with PR Flex-20 polymer additive, at UAH 7,062/t. Its price is lower than similar materials modified with polymers, which cost UAH 7,211-7,425/t according to the data of SE “NIRI”.
Crushed stone M100-300 will cost UAH 73.47 million at a price of UAH 640/t, although it is offered cheaper on the market – from UAH 350 to 450/t.
Sand-crushed mixture C5 was laid at 825 UAH/cubic meter. m, while the average price in Ukraine is UAH 1,030/cubic meter. m, and at other tenders it cost from 598 to 881 hryvnias/cubic. m.
Crushed stone fractions of 40-70 mm and 20-40 mm were laid at 824 hryvnias/cubic. m, which exceeds the average market price (712 hryvnias/cubic m) and prices at other tenders (526-743 hryvnias/cubic m).
Side stones were calculated at 1,650 hryvnias/m, although on the market they cost from 380 to 1,500 hryvnias/m.
Prices for sand, reinforcement and concrete mixes correspond to market prices.
The expected amount of the project was UAH 1.57 billion.
Construction of the road to the airport, which is currently inactive due to the war, began back in 2010, but was postponed several times due to lack of funding.
We will remind:
Municipal enterprise “Directorate of construction of road and transport facilities of the city of Kyiv” of the Kyiv City State Administration October 30 announced tenders for the design and construction of the first stage of the road to the airport “Kyiv” (Zhulyany) with a total expected cost of 1.56 billion hryvnias.
”, — write: epravda.com.ua
About this write Our money linked to the data in the Prozorro system.
The 2.8 km long road will connect Valeriy Lobanovsky Avenue with the airport in Solomyansky district.
The project involves the construction of a two-lane road, a bicycle lane, sidewalks, safety lanes, an overhead pedestrian crossing, as well as the installation of traffic lights, sewage treatment plants, and retaining walls.
Construction is scheduled to be completed by July 2026. Funding will be limited in 2024, UAH 1.16 billion is planned for 2025, and the rest in 2026.
Four companies took part in the tender, including Ukratomenergobud, whose cheapest offer (1.36 billion UAH) was rejected due to documentation problems. As a result, the winner was the Mostador Group consortium with an offer of UAH 1.47 billion.
The consortium includes six companies, including Bridge Construction Unit No. 112 and KP Shlyakhbud Invest, which will provide the main resources for construction. The total income of the consortium members in 2023 amounted to UAH 2.09 billion.
Asphalt concrete will be supplied by BK Zorya LLC, and the main works will be performed by Shlyakhbud Invest and Bridge Construction Unit No. 112.
As Our Money found out, in the information of resources, the largest amount – UAH 92.26 million – is provided for fine-grained asphalt concrete with PR Flex-20 polymer additive, at UAH 7,062/t. Its price is lower than similar materials modified with polymers, which cost UAH 7,211-7,425/t according to the data of SE “NIRI”.
Crushed stone M100-300 will cost UAH 73.47 million at a price of UAH 640/t, although it is offered cheaper on the market – from UAH 350 to 450/t.
Sand-crushed mixture C5 was laid at 825 UAH/cubic meter. m, while the average price in Ukraine is UAH 1,030/cubic meter. m, and at other tenders it cost from 598 to 881 hryvnias/cubic. m.
Crushed stone fractions of 40-70 mm and 20-40 mm were laid at 824 hryvnias/cubic. m, which exceeds the average market price (712 hryvnias/cubic m) and prices at other tenders (526-743 hryvnias/cubic m).
Side stones were calculated at 1,650 hryvnias/m, although on the market they cost from 380 to 1,500 hryvnias/m.
Prices for sand, reinforcement and concrete mixes correspond to market prices.
The expected amount of the project was UAH 1.57 billion.
Construction of the road to the airport, which is currently inactive due to the war, began back in 2010, but was postponed several times due to lack of funding.
We will remind:
Municipal enterprise “Directorate of construction of road and transport facilities of the city of Kyiv” of the Kyiv City State Administration October 30 announced tenders for the design and construction of the first stage of the road to the airport “Kyiv” (Zhulyany) with a total expected cost of 1.56 billion hryvnias.