Metro to Vynohradar: The Supreme Court put a point in a case of 140 million

Metro to Vynohradar: The Supreme Court put a point in a case of 140 million Kyiv City Prosecutor’s Office

The Supreme Court has put a stop in the case of recovery of more than UAH 139 million from the company “Kyivmetrobud”which was to build a metro from the cheese to the vineyard, but instead put the allocated money for a deposit.

About it reports The press service of the Kyiv City Prosecutor’s Office.

In 2021, the Capital Prosecutor’s Office appealed to the court to recover the interest in the amount of more than UAH 139 million in favor of the capital community.

The case has been considered by the courts repeatedly. In April and October 2024, the Economic Court of Kyiv and the Northern Appeal Court of Appeal fully satisfied the claim of the prosecutor and decided to recover interest from the contractor to the capital organization of the capital.

Disagreeing with the said court decisions, the contractor appealed them to the Supreme Court, which refused to satisfy the cassation complaint of the company and left the decision of the courts of the previous instance.

Read more at the link: The train does not go. Why don’t they build a subway on a vineyard?

First deputy nickname Mykola Povoroznik: Metro – as a door. Thirteen years they opened and one day bars – and the handle disappeared

Maxim Shkil: The state financed the protection of energy objects from rockets by 10%

We remind:

New stations of the Mistytska and Pravda Prospect in Kiev were built in 2019. It was planned that they would be opened in December 2021, And their budget will be almost billion UAH.

In September 2021, Kyivmetrobud, which was the general contractor of the construction of two stations for the Vynohradar, asked to postpone the term of the contract. The builders then stated that they did not have time to finish the stations by the end of 2021.

The company appealed to the court to postpone the delivery time from November 2021 to May 2023. In February 2023, Kyivmetrobud restored the construction of the subway to the Vynohradar, but active construction was not carried out in the fall of 2023.

Later “Kiev Metro” tore The contract for the construction of the subway branch for the vineyard due to the breakdown of construction.

The next general contractor was Maxim Shkil’s Autonomic Company.

”, – WRITE: epravda.com.ua

Metro to Vynohradar: The Supreme Court put a point in a case of 140 million Kyiv City Prosecutor’s Office

The Supreme Court has put a stop in the case of recovery of more than UAH 139 million from the company “Kyivmetrobud”which was to build a metro from the cheese to the vineyard, but instead put the allocated money for a deposit.

About it reports The press service of the Kyiv City Prosecutor’s Office.

In 2021, the Capital Prosecutor’s Office appealed to the court to recover the interest in the amount of more than UAH 139 million in favor of the capital community.

The case has been considered by the courts repeatedly. In April and October 2024, the Economic Court of Kyiv and the Northern Appeal Court of Appeal fully satisfied the claim of the prosecutor and decided to recover interest from the contractor to the capital organization of the capital.

Disagreeing with the said court decisions, the contractor appealed them to the Supreme Court, which refused to satisfy the cassation complaint of the company and left the decision of the courts of the previous instance.

Read more at the link: The train does not go. Why don’t they build a subway on a vineyard?

First deputy nickname Mykola Povoroznik: Metro – as a door. Thirteen years they opened and one day bars – and the handle disappeared

Maxim Shkil: The state financed the protection of energy objects from rockets by 10%

We remind:

New stations of the Mistytska and Pravda Prospect in Kiev were built in 2019. It was planned that they would be opened in December 2021, And their budget will be almost billion UAH.

In September 2021, Kyivmetrobud, which was the general contractor of the construction of two stations for the Vynohradar, asked to postpone the term of the contract. The builders then stated that they did not have time to finish the stations by the end of 2021.

The company appealed to the court to postpone the delivery time from November 2021 to May 2023. In February 2023, Kyivmetrobud restored the construction of the subway to the Vynohradar, but active construction was not carried out in the fall of 2023.

Later “Kiev Metro” tore The contract for the construction of the subway branch for the vineyard due to the breakdown of construction.

The next general contractor was Maxim Shkil’s Autonomic Company.

Related posts

Spain has announced a military aid package for a billion euro

pravda.com.ua

Air Force: Pre-4 Russian Tu-95 ms made launches of winged missiles

pravda.com.ua

ООН ухвалила резолюцію з вимогою до Росії негайно вивести війська з України

censor.net

Leave a Comment

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More