“After the missile shelling of the National Children’s Specialized Hospital “Okhmatdit” in July 2024, the institution is actively undergoing restorative work. Since then, a number of hospital facilities have already been rebuilt. About it reports the NSSL “Okhmatdit”. In Okhmatdita it is necessary to restore administrative, medical-diagnostic, surgical and toxicological buildings, as well as a transformer substation. Currently in the hospital managed to restore the work of all wards in the corps that survived”, – WRITE ON: ua.news
After the missile shelling of the National Children’s Specialized Hospital “Okhmatdit” in July 2024, the institution is actively undergoing restorative work. Since then, a number of hospital facilities have already been rebuilt.
About it reports NSSL “Ohmatdit”
In Okhmatdita it is necessary to restore administrative, medical-diagnostic, surgical and toxicological buildings, as well as a transformer substation.
Currently, the hospital has managed to restore the work of all departments in the corps that survived or have undergone partial damage, as well as carry out priority anti -cavities to protect the new building.
IN medical and diagnostic The housing has already been completed with priority anti -avarium work and technical supervision. A contract for the development of project documentation was also signed, and in the first half of May, the hospital plans to announce the procurement procedure for major repairs.
IN Surgical The housing after the shelling was conducted a technical examination, a medical task and a program were developed, and a report on the evaluation of the damage caused was approved.
IN toxicological The building, which is an architectural monument, has announced the procurement procedure for conservation work. The beginning of the work is planned for May 2025.
Administrative The building, which is also a monument of architecture, already has scientific and projection documentation. The announcement of the purchase of construction work on the conservation of this building is planned for May 2025.
Of Transformer substationa contract with Ukrenergo was signed for the development of pro-economic documentation. The facility recovery equipment has already been delivered to the hospital. In the near future, the management of Ohmatdit will announce a tender for the construction of a transformer substation from scratch.
Recall that the Ministry of Health planned to announce a tender for overhaul of the new building of the National Children’s Specialized Hospital “Okhmatdit” in early May. The expected cost of renewable work is UAH 396 million.
Earlier, we wrote that the Cabinet of Ministers of Ukraine made a decision on redistribution of about UAH 6.3 million for urgent work at the National Children’s Specialized Hospital “OHMATDIT”.
We will remind, the children’s hospital “Okhmatdit”, which was injured from the Russian rocket attack on July 8, partially resumed work on July 16, 2024.